London Gateway Berth 4
Working with GPS MACS, TILT were commissioned to design a temporary work scheme to enable the installation of a 300m of scour mats from a construction barge at the new berth.
The innovative truss frame allowed the mats to be installed as a never been done before 30m long single lift.
The system, including hydraulic actuators, delivered installation tolerance of 150mm in 25m of water .